RCC Slab and Beams
1 Beam bottom’s line, level & width should be checked.
2 Beam side’s line, level & plumb should be checked.
3 Beam to beam measurements shall be checked as per architectural drawings.
4 Individual level & diagonall of each slab bay shall be checked.
5 Slab thickness level shall be marked with nails on the peripheral beam’s outer sides.
6 Slab thickness & beam depths should be checked .
7 Deshuttering oil shall be applied to beam/slab shuttering.
8 Formwork of stairacse shall be checked for dimensions of tread and riser, level of treads, plumb of risers.
9 Reinforcement shall be checked for beams and slab as per R.C.C drawing
10 Proper cover for bottom /sides shall be checked for beams and slab
11 Electrical points ,electrical piping (conduits)/fan hooks shall be checked as per drawing.
12 Proper number of chairs shall be provided for slab.
13 Dowels (if any) required to be provided for elevational feaures / future extentions.
14 Check the availability of required labour strength, mixer, lift, vibrators, masons, weigh batcher, diesel/petrol and plastic sheets etc before start of concreting.