RCC Slab and Beams

1 Beam bottom’s line, level & width should be checked.

2 Beam side’s line, level & plumb should be checked.

3 Beam to beam measurements shall be checked as per architectural drawings.

4 Individual level & diagonall of each slab bay shall be checked.

5 Slab thickness level shall be marked with nails on the peripheral beam’s outer sides.

6 Slab thickness  & beam depths should be checked .

7  Deshuttering oil shall be applied to beam/slab shuttering.

8 Formwork of stairacse shall be checked for dimensions of tread and riser, level of treads, plumb of risers.

9 Reinforcement shall be checked for beams and slab as per R.C.C drawing

10 Proper cover for bottom /sides shall be checked for beams and slab

11 Electrical points ,electrical piping (conduits)/fan hooks shall be checked as per drawing.

12 Proper number of chairs shall be provided for slab.

13  Dowels (if any) required to be provided for elevational feaures / future extentions.

14 Check the availability of required labour strength, mixer, lift, vibrators, masons, weigh batcher, diesel/petrol and plastic sheets etc before start of concreting.